Job Reports > Sheet Pile > Holdfast Shores
Holdfast Shores
Glenelg South Australia
60 Berth Boat Basin
The Holdfast Shores Consortium of which Baulderstone-Hornibrook
were a lead member, was responsible for the Holdfast Shores Development
in Glenelg, South Australia.
This involved the construction of a 60 berth boat basin for which
Steelcom supplied LX32 sheet pile to form a hard vertical face.
The boat basin bed level is at RL –6.0 AHD and the adjoining
building levels at RL 3.0 ADH, which was achieved using sheet-piles
that were also incorporated into the adjoining buildings’ basement
structures.
The sheet-piling solution provided the physical “traditional
dock” look the architects desired. The sheet-piling solution
also assisted to preserve precious land when compared to battered
slop with rock revetment.
 |